Building automation mandatory from 70 kW: EPBD and § 56 GModG

The recast EU Energy Performance of Buildings Directive (EPBD) requires non-residential buildings whose heating, air-conditioning or combined ventilation systems exceed 70 kW to have building automation and control systems and automatic lighting controls by the end of 2029. Germany has transposed this in § 56 of its Building Modernisation Act (GModG), in force since 29 July 2026. What the system must do, who is affected and what can be retrofitted wirelessly.

70 kWrated output from which the obligation applies
2029deadline: by 31 December, existing and new buildings
6capabilities the system must have in Germany (§ 56(2) GModG)
2027automatic lighting controls above 290 kW (EPBD); above 70 kW: 2029
5,000euros maximum fine in Germany if the system is missing

Who is affected

Scope

Article 13(9) EPBD obliges all EU member states to require building automation and control systems in non-residential buildings where technically and economically feasible: by 31 December 2024 above 290 kW, by 31 December 2029 above 70 kW. The directive had to be transposed by 29 May 2026.

In Germany, § 56(1) GModG applies to non-residential buildings – offices, administration, schools, practices, retail, hotels or production with an office section – if one of the following systems has a rated output of more than 70 kilowatts, for existing and new buildings alike. The previous German rule (§ 71a GEG) applied only above 290 kW.

SystemObligation from
Heating systemmore than 70 kW rated output
Combined space heating and ventilationmore than 70 kW rated output
Air-conditioning systemmore than 70 kW rated output
Combined air-conditioning and ventilationmore than 70 kW rated output
Rule of thumb from the German technical literature: 70 kW of heating output corresponds roughly to 700 to 1,400 m² of heated floor area. A building is exempt only if fitting the system is technically impossible or economically unreasonable. Residential buildings are not covered by § 56 GModG.

What the system must be able to do

§ 56(2) GModG · Art. 13(10) EPBD

The law does not prescribe a product but capabilities. The EPBD lists them in Article 13(10); the German § 56(2) GModG spells them out in six points. The system must be able to:

No.RequirementWhat it means in practice
1Continuously monitor, log, analyse and adjust the consumption of all main energy carriers and all technical building systemsRecord and evaluate meters for electricity, heat, gas etc. continuously – not read them once a year
2Make the data available via a common, freely configurable interfaceEvaluation independent of the manufacturer: open protocols instead of a closed island
3Set reference values for the building’s energy efficiencyStore target and benchmark values against which operation is measured
4Detect efficiency losses of technical building systemsIdentify deviations automatically, e.g. heating with the window open
5Inform the operator about possible improvementsNotifications and reports to those responsible
6Monitor indoor environmental qualityNew compared with the previous rule: measure CO2, temperature and humidity in the room continuously (EPBD: by 29 May 2026)

Monitoring indoor environmental quality

§ 56(2) No. 6 GModG · Art. 13(10)(d) EPBD

Neither the EPBD nor the GModG defines “indoor environmental quality” in detail. Practitioners use the indoor climate categories of EN 16798-1 and, in Germany, the technical rules for workplaces. In practice, CO2 as an indicator of ventilation, air temperature and relative humidity are measured – continuously and room by room, not as spot checks.

QuantityGuidanceSource
CO2below 1,000 ppm harmless; 1,000 to 2,000 ppm check and improve ventilation; above 2,000 ppm further measuresGerman workplace rule ASR A3.6
Air temperatureshould not exceed 26 °C; above that, graded duties for the employerGerman workplace rule ASR A3.5
Relative humidity, temperatureindoor climate categories for designEN 16798-1

Wireless sensors with solar cells measure CO2, temperature and humidity without cables and without battery-change rounds. How many sensors a building needs and where they go is explained in our planning articles.

CO2 as a control parameter →

Building sensors: which sensors an office building needs →

Lighting: automatic, zoned, with occupancy detection

§ 56(6) GModG · Art. 13(12) EPBD

In addition to the automation system, Article 13(12) EPBD requires automatic lighting controls in non-residential buildings – above 290 kW by 31 December 2027, above 70 kW by 31 December 2029 – suitably zoned and capable of occupancy detection. Germany’s § 56(6) GModG sets the 70 kW / 2029 requirement. In practice this means:

  • Create zones by use – workstations, meeting rooms, corridors – instead of one switch for the whole floor.
  • Presence detectors per zone switch or dim the lights according to occupancy; daylight can be included as well.
  • In existing buildings without new cables: wireless presence detectors send to a DALI controller, which controls the luminaires via the existing DALI line.
  • Data protection: presence detectors without cameras record occupancy per room, not people.

The occupancy data that controls the lighting also helps the heating: an empty room needs neither light nor comfort temperature.

Use case: lighting by presence →

What is a DALI ballast? →

Retrofitting during operation – wirelessly

Existing buildings

Most of the affected buildings already exist. Pulling cables for sensors means chasing walls, dust and downtime. With battery-free EnOcean wireless technology, the system is built in four steps:

Step 1Fit the sensorsCO2, temperature, humidity and presence sensors are glued or screwed in place – powered by a solar cell, no cable.
Step 2Mount the receiversEnoDisc® receivers on the ceiling, powered via PoE; up to 32 receivers per gateway.
Step 3Connect the gatewayThe VL-700 BASE 2 gateway handles up to 500 sensors and shows the values in the ECS Dashboard – no licence per sensor.
Step 4Hand over the dataValues go to the building management system and energy management via MQTT, Modbus TCP, BACnet/IP and BACnet/SC or KNX.

Which requirements we cover – and which we don’t

Classification

A compliant system usually consists of several building blocks. We supply the room level and the open data handover; the evaluation of all main energy carriers is usually done by the building management system or monitoring software to which the gateway connects.

RequirementBuilding block from DEUTA ControlsUsually comes from
Indoor environmental qualityWireless CO2, temperature and humidity sensors, in-room display EnoSign®–
Lighting with occupancy detectionWireless presence detectors and DALI controllersLuminaires and electrical installation
Open interfaceVL-700 BASE 2: MQTT, Modbus TCP, BACnet/IP, BACnet/SC, KNX TP–
Room-by-room control (§ 63 GModG)Individual room control on the VL-700 BASE 2 with temperature sensor and window contact–
Monitoring consumptionCurrent measurement per phase in sub-distribution boards and outgoing circuits, wireless – not calibratedMeters under the Measuring Instruments Directive, heat and gas meters, monitoring software
Benchmarks, losses, notificationsRaw data from the room for evaluationBuilding management system or monitoring software
For billing and calibrated energy measurement, a meter under the Measuring Instruments Directive (MID) is still required – our current measurement is for monitoring, not billing.

Use case: retrofitting energy monitoring →

Use case: individual room control →

EnOcean and DALI gateways: Modbus TCP, KNX, MQTT →

Additionally for new buildings in Germany

§ 56(3) GModG

For a new non-residential building, § 56(3) GModG raises the bar:

  • Building automation at least to automation level C of DIN/TS 18599-11:2025-10 for systems above 70 kW, level B for systems above 290 kW.
  • Technical commissioning management including the balancing of the building services – for heating over at least one heating period, for cooling over at least one cooling period.
  • The connected systems must communicate with each other and work with devices from different manufacturers.

Deadlines, transition and fines in Germany

§ 56(4), § 108 GModG

In Germany the deadline for existing and new buildings is the end of 31 December 2029. For systems installed in the three years before 1 January 2027 that do not meet paragraph 2, § 56(4) provides a transition rule with retrofitting after 2029 and a ten-year period – the technical literature reads the calculation of this period differently.

RuleContent
Deadlineby the end of 31 December 2029 (system under para. 1 and lighting under para. 6)
Exemptionif fitting is technically impossible or economically unreasonable
Transitionpara. 4: systems from the three years before 1 January 2027 may be retrofitted after 2029, period of ten years
Fineanyone who intentionally or recklessly fails to equip a non-residential building contrary to § 56(1), or does so incorrectly or late, commits an administrative offence – fine up to 5,000 euros (§ 108)

Checklist for owners and planners

In seven steps
  1. Determine the rated output of the heating, air-conditioning and ventilation systems – if one exceeds 70 kW, the obligation applies.
  2. Survey the building: Is there a building management system? Which meters, which interfaces, which lighting control?
  3. List the gaps against the required capabilities and the lighting requirement.
  4. Plan the indoor climate: quantities (CO2, temperature, humidity), sensors per room or area, display for occupants.
  5. Plan the lighting: define zones, presence detectors per zone, control via DALI.
  6. Define the data path: which open interface does the building management or monitoring use – MQTT, Modbus TCP, BACnet or KNX?
  7. Schedule and document implementation by the end of 2029; where an exemption may apply, record the reasons in writing.

Frequently asked questions

7 questions

Does the obligation apply to existing buildings?

Yes. Both the EPBD and the German § 56 GModG cover existing and new non-residential buildings whose heating, air-conditioning or combined ventilation system exceeds 70 kW rated output. The deadline is 31 December 2029.

From what building size am I affected?

What counts is the rated output of the system, not the floor area. As a rough rule of thumb, 70 kW of heating output corresponds to about 700 to 1,400 m² of heated floor area.

Does the obligation apply to residential buildings?

No, Article 13(9) EPBD and § 56 GModG concern non-residential buildings. For new and major-renovated residential buildings the EPBD sets separate monitoring and control requirements.

What does “monitoring indoor environmental quality” mean?

The law does not define the term in detail. In practice, CO2, air temperature and humidity are measured continuously and room by room; EN 16798-1 provides guidance.

Does lighting have to be controlled by presence?

Automatic lighting controls are mandatory. The EPBD requires them to be suitably zoned and capable of occupancy detection; § 56(6) GModG says they should be. Presence detectors per zone are the usual solution.

What happens in Germany if the system is missing?

Anyone who intentionally or recklessly fails to equip a non-residential building contrary to § 56(1) GModG, or does so incorrectly or late, commits an administrative offence; the fine is up to 5,000 euros (§ 108).

Can this be retrofitted in existing buildings without new cables?

At room level, yes: wireless sensors with solar cells for indoor climate and presence, receivers powered via PoE and a gateway with open interfaces. Meters and the evaluation of all energy carriers usually come from the building management system or monitoring software.

Status and sources

Status: 23 November 2026. Directive (EU) 2024/1275 (EPBD), Article 13(9), (10) and (12) and Article 35. Germany: §§ 56, 63 and 108 of the Building Modernisation Act (GModG) as amended by the Act of 23 July 2026, Federal Law Gazette 2026 I No. 226, in force since 29 July 2026. Floor-area rule of thumb after M. Krödel, white paper on the GModG requirements for building automation, IGT, 08/2026. Not legal advice – the official wording is authoritative; national transposition differs between member states.

Plan the retrofit

Are you planning a non-residential building above 70 kW or retrofitting one? We put together sensors, receivers and gateway for indoor climate, presence and lighting – with an open handover to your building management system.